A rendered image of Selene Palm Springs, surrounded by palm trees, with a busy road in front.

Selene Palm Springs

Key Updates and Actions for Stakeholders


Upcoming Meeting Dates: May 14, 2026 | June 11, 2026 | July 9, 2026 | Aug 13, 2026 | Sep 10, 2026


February 12, 2026

1. Introductions

The meeting commenced with introductions of all attendees. Notably, Robert Mallia, Regional Vice President of Architecture & Construction for The Lifestyle Group at Hyatt, was present as well as Lauri Kibby, the local partner in Selene Palm Springs, and Eran Nornberg, the representative of the New York majority partner of Selene Palm Springs, the owner/developer of the Dream Project. Robert’s role brings critical oversight and expertise to the project, ensuring alignment with Hyatt standards and strategic goals. Eran and Lauri and responsible for the daily activities of the development including oversite of all the consultants and contractors for the project.

 

2. Project History and Updates

The Dream Hotel project has undergone several phases:

  • Pre-Covid Construction: Initial groundwork and construction activities began prior to the Covid-19 pandemic, setting the foundation for future progress. Work includes the completion of the foundation work for the hotel structure.
  • The effect of Covid-19 on the project: All work at the site was stopped due to Force-majeure and financing turmoil.
  • Post Covid-19 adjustments: Project and program had to be adjusted to correspond to market change and making the project more attractive for financing.
  • Team Adjustments: Changes in team composition were implemented to address evolving project needs and optimize performance.
  • General Contractor Selection: Interviews were conducted and Suffolk Construction was chosen as the General Contractor to build the project.
  • 50% Construction Documents (“CD”) were completed and cost review: Following the completion of 50% CD the project cost was evaluated. Due to changes in the economy (including new tariff imposed on construction supply), a rigorous Value Engineering (VE) process was undertaken to reduce construction cost.
  • Implementing VE changes into CD and create an Interim Gross Maximum Price of construction (“IGMP”): Once completing the VE process the team moved to incorporating all of the changes into the construction documents with a target of March 30th to have fully incorporated the changes so that an IGMP (Interim Guaranteed Maximum Price) can be established and financing discussions can continue
 

3. Community Concerns and Actions

The project team remains empathetic to community concerns and is committed to ongoing engagement:

  • Monthly Meetings: Regular meetings are held with community representatives to foster open dialogue and address feedback every 2nd Thursday of the month in the Palm Grove room at the Convention Center.
  • Attendance: We asked that community members submit questions at info@selenepalmsprings.com and we will endeavor to answer at the monthly meetings.
  • Email Updates: Timely email communications keep stakeholders informed of progress and actions once construction begins. Major announcements will be posted on the website.
  • Site Maintenance: The team maintains the project site by ensuring the fence is secure, removing trees and soil as necessary, and performing consistent perimeter cleaning to preserve neighborhood appearance.
 

4. Ownership Commitment

Ownership is fully committed to the project’s success:

  • Equity Investment: We have made and continue to make a substantial equity contribution (hundreds of thousands) on a monthly basis to support the project, its consultant and contractors.
  • Design/Engineering Work: Design and engineering work continues, ensures our project is meets compliance to state and local code.
  • City Communication: We have ongoing communication with city officials to ensure they are aware of our progress and that we meet the city’s requirements for the project.
  • Model Room: Ownership is starting the construction of the Model Room and the site investigation which are required in order to start construction.
  • We are scheduled to submit drawings for permit March 31st and are on target for that submittal date
 

3. Next Meeting Details

The next meeting is scheduled for March 12th and every month until start of construction on the 2nd Thursday of every month. We will endeavor to bring a different member of our team at each meeting. with the agenda to include updates on construction progress, community engagement, and any outstanding action items. Details regarding time and location will be shared via email to all stakeholders.


Community Meeting Summary

March 12, 2026
Attendees: Lauri Kibby, Eran Nornberg, Bruce Greenfield

The meeting focused on recent project progress and upcoming milestones for the development.

Participants reviewed the work completed over the past several months, including:
(i) the completion of the value engineering (VE) exercise (all VE-related changes have now been incorporated into the project drawings, and the plans will be ready for submission to the City by March 30 to begin the permitting process),
(ii) finalizing the amendment to the agreements with the City, which was successfully negotiated and approved at the City Council meeting on March 11, 2026,
(iii) meetings with the City’s Planning, Building & Safety, and Engineering departments, and
(iv) the replacement of the fence cover that was damaged by recent high winds 

Ongoing efforts include further advancement and refinement of the construction and interior drawings, and maintaining the perimeter fencing and exterior condition of the project site (the fencing has been updated and has withstood the most recent wind conditions well). In addition, the team is also currently working on the CC&Rs for the condominium portion of the project, preparations are underway to build out a model room, which will support completion of final construction drawings and future marketing and financing efforts.

Future work includes pursuing the Pink Report in order to establish an interest list for condominium reservations. The project team is also planning to establish a sales office, with the goal of beginning condominium sales in January 2027.


Meeting Summary

April 9, 2026
 

Overview

The meeting was held on April 9, 2026. Ownership was represented by Eran Nornberg and Lauri Kibby; The City was represented Wayne Olsen. The representatives provided a detailed update and held a Q&A discussion.

 

Review of Structural Engineering & Existing Conditions

  • The original structural engineer has completed an evaluation of the existing structure, confirming that it meets requirements and can support full build-out of the project. A formal letter documenting this has been issued and is being uploaded by the architect to the city’s system.
  • Some minor remedial work is required, including cleaning/sanding corroded rebar, but testing showed that the installed rebar is higher grade and larger than originally specified, giving additional comfort on capacity.
  • The city is actively reviewing these structural submissions, asking questions, and the project consultants are responding as part of ongoing coordination.
 

Construction Documents, Contractor & GMP Process

  • Construction documents were released to the City on March 31, enabling the team to send drawings to the general contractor (Suffolk).
  • Suffolk is now bidding out the project to subcontractors in order to establish an Interim GMP (IGMP), expected around mid-May.
  • Once the IGMP is received, the team will prepare and release a financing package (“financing book”) to potential lenders/investors.
  • A final Guaranteed Maximum Price (GMP) is targeted for August, which will then allow finalization of the overall project budget and execution of finance documents.
 

Financing Status & Timeline

  • The full financing commitment has not been secured as of yet, but the consultant has identified financing partners who are interested in participating. Our financing consultant is assembling the capital stack, and various group remains engaged.
  • There is strong interest from Middle Eastern financing groups (two groups specifically) has been noted for either equity or loan financing.
  • After the IGMP in mid-May, the project goes to market; lenders begin due diligence, reviewing documents and legal structure while knowing the budget is roughly ±10% of the IGMP estimate.
  • Once LOIs are issued and signed, the developer must fund a six‑figure due diligence and legal budget, enabling lenders to complete 2–3 months of due diligence, documentation drafting, and legal review.
  • The GMP is targeted for late August and becomes an exhibit to final loan documents, and execution of loan documents is intended by end of September, so that construction can commence in October.
 

Schedule & Key Milestones

  • Target construction starts (mobilization): September/October of this year, assuming financing is secured by July–September milestones.
  • Hotel opening target: December 2028.
  • It was noted that the start of construction does not mean that heavy construction will commence but rather early activities will start which include site mobilization as well as the following activities:
    • Filling the excavation,
    • Setting up site offices and power,
    • Remedial work prior to vertical construction.[1]
 

Project Phasing, Permits & Construction Strategy

  • The project consists of multiple buildings on approximately eight acres, including: 
    • Hotel + condo-hotel tower on one shared garage/foundation
    • North condominiums (12 units)
    • South condominiums along Amado and Caballeros (28 units)
  • The City has structured the project under three separate permits:
    • Hotel + condo-hotel tower (single permit)
    • North condominiums (second permit)
    • South condominiums (third permit)
  • All three areas are intended to start construction concurrently, primarily to: 
    • Optimize concrete crews and trades across buildings in sequence,
    • Avoid remobilization costs
    • Improve economies of scale
 

Program: Hotel, Condos, Condo-Hotel & Operations

  • The project includes: 
    • A traditional hotel component.
    • A condo-hotel
    • High-end residential condominiums (north and south buildings) with large units aimed at luxury buyers.
  • Simultaneous opening: The hotel and all condo components are planned to open together, not in phases, to maintain the pricing power and positioning of the condos and present a fully completed, non-construction-site environment to buyers.
 

Target Buyer Profile & Market Positioning

  • The development is positioned as an “oasis in the middle of the city” with extraordinary landscaping, extensive food & beverage (F&B) offerings, multiple bars, workspaces (indoor/outdoor), and a strong art program.
 

Site Conditions, Fencing & Maintenance

  • There was discussion of the site fence, including blue Suffolk-branded fencing and concerns about aesthetics, wear, and security (people entering/exiting the site).
  • Ownership discussed the city’s request for less branding and more decorative treatments, leading to the current solution.
  • The developer confirmed there is regular site maintenance (fence upkeep and general cleaning), acknowledging wind and sun degrade fence materials over time.
  • Once the GC fully mobilizes, ongoing site appearance and fence maintenance will be part of the contractor’s daily obligations.
 

Traffic, Access & Convention Center Coordination

  • Primary hotel entrance: Alvarado; this is also intended as the construction entrance, with exit on Caballeros, creating a traffic flow across the site from Alvarado → Caballeros.
  • The Convention Center is planning building renovations and a broader urban planning/streetscape effort between the center and downtown, including more shade and walkability.
  • It was noted that having hotel construction overlap with some public realm improvements might ultimately be positive if both are completed around the same time.
 

Land Tenure & Ownership

  • The land is confirmed to be fee simple, not leasehold
 

Developer Commitment & Risk/Return Context

  • The developer highlights that approximately +$50 million has already been invested in the project, noting that delays are costly making every day of delay financially significant so the team is focused on moving the project forward as quickly as possible.
  • They emphasized a strong personal and team commitment and focus on pushing the project forward.
  • They acknowledge global uncertainties (COVID, Middle East conflict, climate issues, political changes) but report continuing positive signals from financiers, while noting the Middle East situation has had some effect on financing sentiment.
 

Political & Macro Commentary (Context, Not Decisions)

  • There is informal conversation about political uncertainty and global instability impacting financing, with references to war in the Middle East and U.S. politics potentially influencing markets.
  • These comments are contextual to risk perception rather than specific project actions.


Community Meeting Overview

May 14, 2026
 

  • Project: Selene Palm Springs hotel and condo development.
  • Format: Monthly neighborhood update meeting, held on the second Thursday of each month; dates are posted on the Selene Palm Springs website.
  • Key Representatives:
    • Eran Nornberg – representing BrookRiver Hotels, based in New York.
    • Lauri Kibby – local full-time resident and co-owner/developer, involved with the project for roughly ten years and responsible for the original entitlements.
 

Ownership and Brand Structure

  • The land and future building are owned by Selene Palm Springs LLC, a California entity.
  • Selene Palm Springs LLC is jointly owned by two California LLCs.
  • Both are owners and developers of the project; they own the land and will own the completed real estate.
  • The Dream Hotel brand was sold to Hyatt, However BrookRiver retained ownership of the real estate where those flags operate.
  • For this project, Selene Palm Springs will retain ownership of the hotel and condos; while Hyatt will manage the hotel under the Dream flag via a branding/management agreement.
  • The structure is analogous to other hotels where one party owns the real estate, another holds the brand (e.g., Hyatt, Hilton, Marriott), and a third manages daily operations.
 

Positioning and Guest Experience Vision

  • The Selene Palm Springs / Dream Palm Springs project is described as a luxury urban resort on approximately 7.8 acres.
  • The "soul" of the Dream brand is to reflect its host community; in Palm Springs it will be an elevated, resort-focused expression.
  • The property is intended to serve both guests and the local community, with public-facing amenities such as a coffee/bakery component envisioned as a neighborhood source for bread, pastries, and coffee.
  • They anticipate strong connectivity with the convention center and future city improvements (walkability, shade, streetscape), creating a local activity hub, especially for residents east of the site.
 

Project History and Current Status

  • Construction originally began in late 2018, completing structural components for the two main buildings before COVID-19 halted progress.
  • Due to the long pause and economic changes, the team revisited and revised the plans.
  • A key recent milestone was meeting a March 31 deadline to submit approximately 80% construction drawings to the City of Palm Springs for review and permitting.
  • Since submission, the team has been holding weekly or near-weekly meetings with city departments, including fire, planning, building, and the city manager's office, to address comments.
  • The city's process sends structural plans to a third-party structural engineer (due to no in-house licensure) while other disciplines are reviewed by planning, fire, and building/safety.
  • The first round of city/third-party comments comprised roughly 20 pages, reflecting the scale of the set (about 1,000 sheets).
  • The project team is now responding with clarifications and design modifications, then resubmitting for a second review, with the expectation of multiple review cycles.
  • The city's third-party review contract includes turnaround time requirements, so the outside engineer must respond within a set number of days, reducing the risk of external delays.
  • The development team expresses strong appreciation for city staff and notes that while the city can be maligned publicly, their own experience has been very positive.
 

Construction, Budgeting, and Financing

  • Near-complete construction documents have been sent to the selected general contractor, Suffolk, a strong, large national construction firm.
  • Suffolk is currently pricing the drawings to establish an Interim Guaranteed Maximum Price (IGMP), a precursor to a final GMP.
  • The ultimate goal is a Guaranteed Maximum Price (GMP) contract, under which Suffolk will commit to delivering the project for a capped amount.
  • Securing a firm GMP is critical for project financing, since lenders require that cost certainty.
  • The team expects to receive the IGMP around mid-June, with an indication it may arrive even earlier.
 

Model Room and Marketing Preparation

  • The team has leased space for a model room.
  • Some design changes have been made, and they are awaiting furniture deliveries before the model room construction can be started.
 

Community Engagement and Transparency

  • The developers emphasize a commitment to transparency with neighbors, acknowledging frustration about the long-vacant, fenced site and explaining "what's going on behind the scenes."
  • Monthly meetings are open to local residents, with summaries posted online so non-attendees can stay informed or share updates with homeowner groups.
  • The city economic development representative (Wayne Olsen) was in attendance, underscoring coordination between Selene Palm Springs and the City of Palm Springs.

Continue your booking